India's 500 GW RE target hinges on LDES scale-up; FY28 viability gap funding key

Benchmarks Nifty23,053.10116.35FEATURED FUNDS★★★★★Motilal Oswal Midcap Fund Direct-Growth5Y Return18.73 % Invest NowFEATURED FUNDS★★★★★UTI Aggressive Hybrid Fund Regular Plan-Growth5Y Return9.04 % Invest NowEnter search…

India's 500 GW RE target hinges on LDES scale-up; FY28 viability gap funding key
Benchmarks Nifty23,053.10116.35FEATURED FUNDS★★★★★Motilal Oswal Midcap Fund Direct-Growth5Y Return18.73 % Invest NowFEATURED FUNDS★★★★★UTI Aggressive Hybrid Fund Regular Plan-Growth5Y Return9.04 % Invest NowEnter search text:
    The Economic Times daily newspaper is available online now. Read Today's Paper India's 500 GW RE target hinges on LDES scale-up; FY28 viability gap funding key enabler: IESA reportPTILast Updated: Oct 30, 2026, 06:45:00 PM ISTSynopsis

    With a target of 500 GW of renewable energy capacity by 2030, India recognizes the urgent need for long-duration energy storage solutions. The India Energy Storage Alliance stresses the pivotal role of viability gap funding to promote quicker adoption of these technologies. Current data reveals substantial solar energy curtailment caused by grid restrictions, highlighting the necessity for strategic policy support and innovative business paradigms.

    New Delhi: India's target of achieving 500 GW of renewable energy by 2030 hinges on rapid expansion of long-duration energy storage, with FY28 viability gap funding as a critical enabler, a report released on Friday said.

    As the focus shifts from capacity addition to the optimisation and integration of renewable resources, scaling up LDES is essential to support grid stability, renewable integration, and energy resilience on the path to net zero, the India Energy Storage Alliance (IESA) said in a statement.

    India's path to achieve 500 GW of non-fossil fuel energy capacity by 2030 now depends on scaling up long-duration energy storage (LDES) technologies, according to a new report by the India Energy Storage Alliance (IESA) in association with Customized Energy Solutions (CES).

    The report, titled 'Long-Duration Energy Storage: Global Outlook and India's Deployment Pathway', identifies the anticipated FY28 viability gap funding (VGF) framework as a key enabler for accelerating LDES deployment and unlocking the full value of India's clean energy transition.

    The report highlighted that over eight months in 2025, India curtailed 2.3 terawatt-hours (TWh) of solar energy due to grid and storage constraints, underscoring the urgent need to enhance grid flexibility and maximise renewable generation.

    Live Events


        With the increasing penetration of variable renewable energy, the ability to capture surplus electricity and dispatch it during periods of high demand or low generation is vital for grid reliability and economic efficiency.

        According to the LDES Council, by 2040, the world will require around 8 terawatts (TW) of LDES capacity, equivalent to 140 TWh of storage.

        In comparison, 117 GW was operational globally in 2025, indicating that deployment rates must increase nearly 50-fold to meet future requirements.

        Achieving this will require an estimated USD four trillion in capital investment, with the potential to unlock approximately USD 540 billion in annual system-wide savings.

        Despite these benefits, the current global project pipeline stands at only 0.22 TW, about 3 per cent of the 8 TW target, signalling significant growth potential and the need for accelerated action.

        IESA President Debmalya Sen said, "India's journey toward a clean and reliable energy future depends on our ability to integrate renewables efficiently and flexibly. Long-duration energy storage is the linchpin that will enable us to maximise renewable utilisation, enhance grid stability, and build resilience into our power system".

        With the right policy support, innovative business models, and technology-neutral investment, India can set a global benchmark for sustainable energy integration and system reliability, Sen added.

        In India, the Central Electricity Authority (CEA) projects a battery energy storage system (BESS) requirement of 34.5 GWh by FY2027.

        To date, 9.3 GWh has been commissioned, with another 195 GWh of projects awarded or under tender.

        However, most of this pipeline is concentrated on short-duration solutions, underscoring the need to diversify towards long-duration technologies that can provide grid balancing and resource adequacy over extended periods.

        The report highlighted a spectrum of emerging storage technologies positioned to address these requirements.

        Flow batteries are suited for daily storage cycles of eight to twelve hours, iron-air batteries offer multi-day flexibility, and solutions such as pumped hydro, compressed air, and thermal energy storage address large-scale and industrial needs.

        The optimal technology mix will depend on specific grid applications, project economics, and deployment environments.

        Policy and financing frameworks will be instrumental in accelerating LDES adoption.

        The report noted the absence of a formal statutory definition for long-duration storage and a dedicated funding mechanism for projects providing eight hours or more of storage in India.
        Add as a Reliable and Trusted News Source Add Now!
        (You can now subscribe to our Economic Times WhatsApp channel)
        Read More News onIndia renewable energy target 2030IESA reportviability gap funding FY28grid stability renewable energyenergy storage technologiesclean energy transition Indiabattery energy storage systemrenewable energy integrationCentral Electricity Authority

        (Catch all the Business News, Breaking News and Latest News Updates on The Economic Times.)

        ...moreless
        (You can now subscribe to our Economic Times WhatsApp channel)
        Read More News onIndia renewable energy target 2030IESA reportviability gap funding FY28grid stability renewable energyenergy storage technologiesclean energy transition Indiabattery energy storage systemrenewable energy integrationCentral Electricity Authority

        (Catch all the Business News, Breaking News and Latest News Updates on The Economic Times.)